Lagoon Decommissioning

Fargo Waste Connection project map

Phase 1: Fargo/West Fargo Wastewater Connection

Background

The City of West Fargo wastewater system currently consists of a series of ten lagoon cells covering 600 acres of land with 460 acres of actual treatment area (440 million gallons allowable storage volume). The lagoons are near hydraulic capacity and current organic loading grossly exceeds the capacity of the primary cells (pond #1 and #3). The deficiency in treating organic material magnifies operational issues such as odor, in which the city has seen an increase in complaints in recent years as the community has grown.

The City of West Fargo decided to address current and future capacity demands by coordinating an agreement with the City of Fargo. This agreement states that West Fargo can send 100% of their wastewater flow to Fargo providing the ability to decommission the existing lagoon system. 

Based on the agreement, West Fargo is responsible to install a conveyance system  that will deliver its wastewater to a connection point at 19th Avenue N. and Ninth Street NE. Fargo will be installing the necessary collection and metering system to this location with a design capacity to accommodate West Fargo’s future demands, which are 6.5 million gallons per day (average) and 14 million gallons per day (peak).

Completed Project

Construction of a 3-mile force main and gravity pipe to convey the wastewater flows from the Northside Regional Lift (SA40) to the Fargo connection point.

Future Phases: Lagoon Decommissioning

Following the connection to Fargo, the City of West Fargo will decommission the lagoons over time, which will reduce sewage odors.

Project Schedule:

2018: Begin construction of 3-mile force main.

2019: Complete construction and begin sending sewage to Fargo

Spring/Summer 2020: West Fargo City Commission to review decommissioning options and costs to approve a plan. 

Fall 2020: City of Fargo sewage treatment facility upgrades scheduled to be completed.

  • This will enable 100% of wastewater to be sent to Fargo.

Spring/Summer 2021: 

  • Status: 
    • Cells 8 and 9 are dry and 10 is seeded
    • Selling rip rap from cell 10
    • Grading lot at SA40 lift station 
  • Next Steps: 
    • Seeding cells 8 and 9
    • Awaiting final permitting on the southern portion

2020-2030: Decommission 90% of lagoons

  • One small lagoon cell will remain active for emergency situations or other solid waste disposal needs.

Goal of completely decommissioning all lagoons by 2030